Demolition of Newark Bridge
Project involved:
- Meeting with clients and structural engineers over project planning
- Enabling works during 24hour shift on Christmas day to allow construction of pads & skids.
- Erection of new bridge by client adjacent
- Dismantling and sliding out of old bridge whilst new bridge was put in place.
- Processing of all steel and removal from site.
- All works completed in 24 hours so main coastline could reopen.
- Regular blood lead monitoring for operatives.

![]()